Oracle stock hits 52-week low as New Mexico blocks pipeline

Oracle Stock Hits 52-Week Low as New Mexico Blocks Pipeline
Oracle Stock Hits 52-Week Low as New Mexico Blocks Pipeline

A New Mexico regulator rejected the pipeline powering Oracle's Project Jupiter data center, sending ORCL to a fresh low. Here is what investors should watch.

Oracle (ORCL) has spent two years telling Wall Street it can build AI infrastructure faster than anyone else. 

A land commissioner in New Mexico just made that harder.

On Monday, Oracle stock fell about 3.5% to a fresh 52-week low, trading near $122 after touching $120.03 earlier in the day.

The trigger for the drop wasn't financial. It was regulatory

New Mexico's top land official rejected, for the second time, a natural gas pipeline meant to power Oracle's "Project Jupiter" data center.

Normally, investors would shrug off a headline like that. However, this time they didn't, and the reason says a lot about where Oracle stands right now.

What New Mexico's decision actually blocks for Project Jupiter

Project Jupiter is a 2.5-gigawatt data center campus in Doña Ana County, part of the wider $500 billion Stargate initiative Oracle and OpenAI are building for AI infrastructure.

Running this data center takes a huge amount of power. The facility relies on on-site fuel cells fed by natural gas.

That gas needs a pipeline to be moved. The proposed route was a 17-mile pipeline from El Paso, built by Energy Transfer (ET), that would cross a short stretch of state trust land.

New Mexico Land Commissioner Stephanie Garcia Richard initially said no to the pipeline application. 

In a July 14 letter, she again denied the rights-of-way, having first rejected the application in March, KOB reported.

Her reasoning was blunt. The project, she wrote, offered little benefit to the state's land trust or local community, while carrying clear environmental risk.

Why the commissioner pushed back:

  • Emissions: Project Jupiter is forecast to emit more than 10 million tons of greenhouse gases a year, more than double the city of Albuquerque's total, according to Santa Fe New Mexican.
  • Water: The campus draws heavily on water in an arid region already under strain.
  • Return: State officials concluded the project would enrich private backers far more than New Mexico's public institutions.
the-exhibition-floor-at-the-nvidia-gtc-conference
A halted pipeline threatens the power supply for one of the largest AI campuses under construction in the U.S. Bloomberg / Getty Images

Why one pipeline denial rattled Oracle stock

A local permit fight would not normally move a mega-cap stock. This one did because of what it threatens next.

Oracle needs Project Jupiter online to compete with cloud hyperscalers on the AI compute market. A blocked pipeline application puts that timeline at risk.

Oracle has already said missing its power schedule would push costs up. Rerouting around state land could add billions to the bill.

Research firm SemiAnalysis now expects power at the site in 2029, not 2027, Pete Dinelli reported. The project still lacks an air quality permit and a gas line.

For a stock already trading on fear, a two-year delay lands hard.

More AI Infrastructure Stocks:

Project Jupiter was set to run entirely on Bloom Energy (BE) fuel cells, a deal Oracle unveiled that could scale to 2.45 gigawatts

If Jupiter slips, every supplier tied to it feels it too.

How the pipeline fight feeds a bigger money problem

The permit denial did not create Oracle's biggest worry. It amplified one already in the room.

That worry is cash. Oracle is spending enormous sums on AI capacity, and the market is nervous about how it pays for that.

Related: Oracle’s stock buybacks: History & investor impact explained

On Monday, CLSA initiated coverage on Oracle with a Hold rating and a $145 price target, Investing.com reported.

That call carried the real weight. CLSA estimated Oracle may need up to $500 billion in capital through 2030 to fund its AI roadmap, and internal cash flow could only cover about a fifth of it. 

The rest would come from debt or equity raises.

The financial pressure points investors are tracking:

  • A capital need that could reach $500 billion by 2030
  • A debt load that has pushed Oracle's credit rating to BBB-, one notch above junk
  • Negative free cash flow tied to a heavy capex ramp

Against that backdrop, any friction at a flagship project reads as one more reason to doubt the plan.

The operating business is still growing

It would be easy to write Oracle off after over a 60% decline from its high. But the underlying numbers argue against that.

Oracle's fiscal fourth-quarter results showed total revenue went up 21% to about $19 billion, with cloud revenue climbing 47%.

The company delivered more than 1.2 gigawatts of data center capacity in 2026 and reported record remaining performance obligations of $638 billion.

The tension is clear. Oracle has the demand and the backlog. What it lacks, at least for now, is a clean path to fund and power the buildout.

What Oracle stock investors should watch next

For readers deciding what to do here, the near-term catalysts are concrete and worth tracking before making a move:

  • The air quality permit. New Mexico's Environment Department has scheduled a hearing, and no approval means no fuel cells.
  • An alternative power route. A reroute or redesign for Jupiter would confirm added cost and delay.
  • Fresh capital. Any large debt or equity raise would show how Oracle plans to close its funding gap, and could pressure the stock further.
  • The next earnings update. Oracle reports first-quarter fiscal 2027 results on September 10.

Oracle remains profitable, its cloud backlog is real, and the average analyst target still sits well above the stock's current price.

However, there is also a real risk. A company funding a historic buildout largely on borrowed money has little room for setbacks, and Monday delivered one.

The pipeline denial did not break Oracle's AI story. It exposed how much of that story still depends on things going right.

Nothing here is a recommendation to buy or sell. It is context, so you can weigh the growth against the balance sheet and decide what fits your own risk tolerance.

Related: Oracle’s stock splits: History & prospects explained

larryellison_pl_210726
larryellison_pl_210726
Read full story on TheStreet

Related News

More stories you might be interested in.

Jamie Dimon says he has seen the numbers and SpaceX’s orbital data centers ‘could actually work’ despite technical, valuation risks
Benzinga·14 hours ago

Jamie Dimon says he has seen the numbers and SpaceX’s orbital data centers ‘could actually work’ despite technical, valuation risks

JPMorgan Chase & Co. JPM CEO Jamie Dimon on Monday called Starlink an "extraordinary product" and said SpaceX’s SPCX plan to build artificial-intelligence data centers in orbit could work, offering a prominent Wall Street endorsement as the newly public company’s shares hover near their IPO price. Dimon Sees Orbital Computing’s Economic Potential Speaking on "The Master Investor Podcast with Wilfred Frost,” Dimon called SpaceX "an extraordinary...

Jensen Huang thinks semiconductors will be the largest industry in the world "by far" — and this might be key to getting Nvidia stock to $500
24/7 Wall St.·1 day ago

Jensen Huang thinks semiconductors will be the largest industry in the world "by far" — and this might be key to getting Nvidia stock to $500

Quick ReadJensen Huang envisions trillions of autonomous AI agents running across factories, homes, and devices, suggesting semiconductor demand is vastly underestimated.Nvidia's valuation has contracted to rank among the cheaper Magnificent Seven stocks, with a Street-high target of $500 implying a 148% gain.Are you ahead, or behind on retirement?...

What's going on with Bloom Energy stock Monday?
Benzinga·1 day ago

What's going on with Bloom Energy stock Monday?

Bloom Energy Corp BE shares are declining Monday. TD Cowen published a note, flagging meaningful delays at two of its largest data center projects. Here’s what you need to know. Bloom Energy shares are retreating from recent levels. Why are BE shares down? TD Cowen Highlights Project Delays and Supply Chain Risks TD Cowen analyst Jeff Osborne maintained a Hold rating and $235 price target. The analyst considers the stock fully valued at current...

Top